Cold water piping systems

Cold water piping systems

Design:. A.M. International Ltd | | | |

Chillers farm steps for cooling Data Center support in N + 1 Backup.
  • Starting with the simulator of the Piping.
  • Concrete casting of the Bases.
  • Welding the plumbing and creating a "water bank" with taps for emergencies and/or maintenance.
  • Performing pressure tests.
  • Chillers crane works.
  • Running and checking the systems in the roof and then running the critical equipment in the data center.