Phases of Data Center Project | | | |
- Clean and leveling.
- Sealing floor.
- Water distribution infrastructure for HVAC units.
- Internal infrastructures for the electricity and communications (copper and optics).
- Supply and connection of air-conditioning units.
- Subsystems: Lighting, control, fire alarm, Pre-action sprinklers.
- UPS systems.
- External WWW connectivity (fiber optic)
- Inserting racks and covering aisles.
- Acceptance and commissioning of the room and populating servers.